Projects
Demonstration Project
Demonstration Project
Ai-Structural was awarded a business investment grant from the Economic Development Office of Orange County, NC. The grant was used to develop and test prototypes of the company’s products. As part of the demonstration project, masons constructed structural reinforcement of two CMU walls. One wall was built using conventional reinforcement materials and methods. In contrast, the second wall was constructed using Ai-Structural’s products and methods.
Ai-Structural was awarded a business investment grant from the Economic Development Office of Orange County, NC. The grant was used to develop and test prototypes of the company’s products. As part of the demonstration project, masons constructed structural reinforcement of two CMU walls. One wall was built using conventional reinforcement materials and methods. In contrast, the second wall was constructed using Ai-Structural’s products and methods.
The construction was documented on video clips provided in this section. The project demonstrated that the Ai-SP method:
- Provided continuous structural reinforcement (from the footing through the CMU walls and through the double top plates). The cables will be connected to the roof trusses in a later phase tying the roof to the footing).
- Made a safer working environment for the masons and other workers (by avoiding contact with exposed vertical rebar).
- Reduced worker fatigue (eliminated the need for masons to lift heavy CMUs at considerable heights over the rebar).
2min 4sec Option D, with no music.mp4
The two masons each had forty years of experience using rebar for structural reinforcement. However, once the masons became familiar with Ai-Structural’s prototypes and methods they indicated they would be receptive to using the new technique on future projects. They appreciated the safer working conditions and the reduced work effort afforded by the new method. Once masons gain more experience with the new method the end result will be safer, more efficient, and cost-effective projects.
The two masons each had forty years of experience using rebar for structural reinforcement. However, once the masons became familiar with Ai-Structural’s prototypes and methods they indicated they would be receptive to using the new technique on future projects. They appreciated the safer working conditions and the reduced work effort afforded by the new method. Once masons gain more experience with the new method the end result will be safer, more efficient, and cost-effective projects.
[AI-SP] (#32-3, 32-4, 42) Installing Short Segments of Rebar to Support Cable.mp4
Installing Short Segments of Rebar to Support Cable
Installing Short Segments of Rebar to Support Cable
[AI-SP] 38, 40 Cutting Cable.mp4
Cutting Cable
Cutting Cable
[AI-SP] (#57) Introducing New Ai-SP Methods and Devices to Mason.mp4
Introducing New Ai-SP Methods and Devices to Mason
Introducing New Ai-SP Methods and Devices to Mason
(#65) Laying CMU over Coiled Cable.mp4
Laying CMU over Coiled Cable
Laying CMU over Coiled Cable
(#79) Feeding Cable through Hollow Core of CMU Speed 4x.mp4
Feeding Cable through Hollow Core of CMU
Feeding Cable through Hollow Core of CMU
035 (#90) Laying Bond Beams on Top of East Wall.mp4
Laying Bond Beams on Top of East Wall
Laying Bond Beams on Top of East Wall
(#91) Pulling Coiled Cable up with Ai-SP Prototype Coil Retriever.mp4
Pulling Coiled Cable up with Ai-SP Prototype Coil Retriever
Pulling Coiled Cable up with Ai-SP Prototype Coil Retriever
037 (#92) Setting Wedge Pins and Connector Clamps on Cable.mp4
Setting Wedge Pins and Connector Clamps on Cable
Setting Wedge Pins and Connector Clamps on Cable
039 (#93B) Connecting Horizontal and Vertical Cables.mp4
Connecting Horizontal and Vertical Cables
Connecting Horizontal and Vertical Cables
038 (#93A&95) Filling Hollow Cores in Bond Beams with Mortar.mp4
Filling Hollow Cores in Bond Beams with Mortar
Filling Hollow Cores in Bond Beams with Mortar
051 (#116) Joining Rebar and Cable with Connector Clamp.mp4
Joining Rebar and Cable with Connector Clamp
Joining Rebar and Cable with Connector Clamp
052 (#117) Holding J-Bolts Temporarily with Wedge Pins.mp4
Holding J-Bolts Temporarily with Wedge Pins
Holding J-Bolts Temporarily with Wedge Pins
053 (#118) Adding Mortar in Bond Beams with J-Bolts.mp4
Adding Mortar in Bond Beams with J-Bolts
Adding Mortar in Bond Beams with J-Bolts
054 (#119) Removing Wedge Pins to Smooth Mortar.mp4
Removing Wedge Pins to Smooth Mortar
Removing Wedge Pins to Smooth Mortar
055 (#120) Smoothing Mortar around J-Bolts.mp4
Smoothing Mortar around J-Bolts
Smoothing Mortar around J-Bolts
056 (#121) Replacing Wedge Pins around J-Bolts until Mortar Cures.mp4
Replacing Wedge Pins around J-Bolts until Mortar Cures
Replacing Wedge Pins around J-Bolts until Mortar Cures
062 (#126) Feeding Cable through First Top Plate.mp4
Feeding Cable through First Top Plate
Feeding Cable through First Top Plate
(#127A) Securing Cable with Connector Clamp for Roof Structure.mp4
Securing Cable with Connector Clamp for Roof Structure
Securing Cable with Connector Clamp for Roof Structure
064 (#128) Completed Demonstration Project.mp4
Completed Demonstration Project
Completed Demonstration Project
(#20) Excavating West Footing (Speed 4x).mp4
Excavating West Footing
Excavating West Footing
(#26) Extending Depth of East Footing (4x).mp4
Extending Depth of East Footing
Extending Depth of East Footing
(#27) Removing Debris from Excavation (4x).mp4
Removing Debris from Excavation
Removing Debris from Excavation
(#29) Backfilling Excavation with Gravel (4x).mp4
Backfilling Excavation with Gravel
Backfilling Excavation with Gravel
(#30) Setting Elevations for Footing (4x).mp4
Setting Elevations for Footing
Setting Elevations for Footing
(#32-1,32-2) Installing Vertical Reinforcement.mp4
Installing Vertical Reinforcement
Installing Vertical Reinforcement
(#32-5) Bending Rebar for Horizontal Reinforcement (4x).mp4
Bending Rebar for Horizontal Reinforcement
Bending Rebar for Horizontal Reinforcement
(#36) Cutting Rebar 4x.mp4
Cutting Rebar
Cutting Rebar
(#45, 46) Pouring Concrete for Footing.mp4
Pouring Concrete for Footing
Pouring Concrete for Footing
(#60) Masons Dodging Rebar During Work (4x).mp4
Masons Dodging Rebar During Work
Masons Dodging Rebar During Work
(#61,63, 64) Working Around Exposed Rebar.mp4
Working Around Exposed Rebar
Working Around Exposed Rebar
020 Straddling Rebar During Masonry Work (#62).mp4
Straddling Rebar During Masonry Work
Straddling Rebar During Masonry Work
(#75, 76, 77, 78) Lifting CMUs over Rebar.mp4
Lifting CMUs over Rebar
Lifting CMUs over Rebar
(#82A) 1x Relifting CMU over Rebar to Match Correct Hollow Core.mp4
Relifting CMU over Rebar to Match Correct Hollow Core
Relifting CMU over Rebar to Match Correct Hollow Core
(#83) Laying Last CMU in First Course of West Wall.mp4
Laying Last CMU in First Course of West Wall
Laying Last CMU in First Course of West Wall
041 (#98) Working Above Exposed Rebar.mp4
Working Above Exposed Rebar
Working Above Exposed Rebar
(#99, 100) Setting Full CMU Over Rebar 4x.mp4
Setting Full CMU Over Rebar
Setting Full CMU Over Rebar
(#103) Setting Half CMUs over Rebar.mp4
Setting Half CMUs over Rebar
Setting Half CMUs over Rebar
045 (#108) Filling Hollow Cores with Mortar (Untied Rebar).mp4
Filling Hollow Cores with Mortar (Untied Rebar)
Filling Hollow Cores with Mortar (Untied Rebar)
046 (#110A) Setting Angle Iron for Window Opening.mp4
Setting Angle Iron for Window Opening
Setting Angle Iron for Window Opening
047 (#110B) Setting Notched CMU.mp4
Setting Notched CMU
Setting Notched CMU
048 (#111) Finding an Alternate Use of Bond Beams.mp4
Finding an Alternate Use of Bond Beams
Finding an Alternate Use of Bond Beams
049 (#114) Laying Bond Beams (West Wall).mp4
Laying Bond Beams (West Wall)
Laying Bond Beams (West Wall)
050 (#115) Laying Final Bond Beam (West Wall).mp4
Laying Final Bond Beam (West Wall)
Laying Final Bond Beam (West Wall)
057 (#122) Setting Modified Bond Beam on Angle Iron.mp4
Setting Modified Bond Beam on Angle Iron
Setting Modified Bond Beam on Angle Iron
(#123A) Lifting Precast Block Lintel.mp4
Lifting Precast Block Lintel
Lifting Precast Block Lintel
059 (#123B) Laying Precast Block Lintel in Course 12.mp4
Laying Precast Block Lintel in Course 12
Laying Precast Block Lintel in Course 12
060 (#123C) Giving a High Five for a Successful Demonstation Project.mp4
Giving a High Five for a Successful Demonstation Project
Giving a High Five for a Successful Demonstation Project
061 (#125) Adding Mortar to Final Bond Beam.mp4
Adding Mortar to Final Bond Beam
Adding Mortar to Final Bond Beam